Commissioning verifies that enrolled components, Interfaces, Cartridges, and BIOS services perform correctly in their installed configuration.
Activation authorizes them to participate in building operation.
Commissioning shall verify, as applicable:
physical presence;
location and orientation;
Interface seating and locking;
structural support;
grounding and bonding;
utility connection;
sealing and leakage;
communication;
identity;
firmware and configuration;
sensor response;
actuator operation;
control authority;
interlocks;
alarms;
safe state;
emergency behavior;
Digital Twin synchronization.
Commissioning may occur at:
component level;
Interface level;
Cartridge level;
subsystem level;
zone level;
building level.
Each commissioned entity shall receive:
commissioning status;
date;
responsible authority;
tests performed;
evidence;
accepted limitations;
- next inspection or maintenance requirement.
- Activation shall occur only after all required commissioning hold points are satisfied.
Activation may authorize:
monitoring only;
limited operation;
temporary operation;
degraded operation;
full operation;
- emergency-only operation.
- A command-capable component shall receive only the control permissions required by its commissioned role.
Commissioning failure shall return the affected entity to a safe, connected-but-inactive, isolated, or faulted state.