7. Regulated Lifecycle Activities
Stable section ID: S05-CON-014-SECTION-8 · 29 content blocks
The Rules shall govern relevant activities throughout the complete lifecycle of System05 assets and buildings.
Regulated activities may include:
- Research and concept development.
- Requirements definition.
- Architecture and design.
- Analysis, simulation, and optimization.
- Material selection and substitution.
- Prototype development.
- Manufacturing and fabrication.
- Quality control and product release.
- Packaging, storage, and transportation.
- Site preparation and installation.
- Human or robotic assembly.
- Connection, locking, sealing, and commissioning.
- Inspection and readiness-for-use approval.
- Operation and monitoring.
- Maintenance, repair, and renewal.
- Software and firmware update.
- Cartridge replacement or functional upgrade.
- Reconfiguration and expansion.
- Ownership or custody transfer.
- Post-event assessment and reoccupation.
- Isolation and temporary shutdown.
- Disassembly and deconstruction.
- Requalification, reuse, refurbishment, or remanufacturing.
- Recycling, recovery, and final disposition.
- Record archiving and identity closure.
Each activity shall identify applicable responsibilities, authorization boundaries, required competencies, safety controls, verification steps, and resulting records.
A change performed during operation shall not be considered less significant merely because the building has already been commissioned. Lifecycle changes capable of affecting safety, compatibility, performance, configuration, or conformance shall remain controlled engineering activities.